Grwyne Fawr Reservoir

THE PROJECT

Grwyne Fawr dam, located in the Grwyne Fawr Valley of the Brecon Beacons National Park, was constructed between 1912 and 1926, with the aim of providing a consistent water supply to the county of Monmouthshire and the growing steel and coal industries in the local area. MMB were commissioned by Dŵr Cymru Welsh Water to inform the design of remedial works required following a Reservoirs Act 1975 Section 10(2) Statutory Inspection of the Reservoir.

Geotechnical Engineering Ltd (GEL) were subsequently appointed as the specialist ground investigation contractor on the project, in order to gather representative information on the ground conditions and dam construction to inform geotechnical design.

THE CHALLENGE

Given the site location at the head of the Grwyne Fawr Valley, perched at an elevation of 547mAOD, the biggest challenge was accessing the site and borehole positions. The 3km section of track from the base of the dam up to the crest is extremely narrow, with no passing places and was in a state of disrepair prior to the fieldwork. The site location made effective communication challenging, given the poor phone network signal.

The dam construction was understood to comprise cyclopean concrete, but the exact nature of the structure, including the extent of voids and the ratio of matrix to clasts, and clast size was unknown. This presented significant potential challenges when constructing boreholes, alongside a highly fractured bedrock stratum.

THE SOLUTION

Several repairs to the access route were conducted prior to the works, to allow for the transportation of drilling plant, equipment and personnel to the exploratory locations. Inclement weather conditions meant the track conditions degraded over time, and additional remediation efforts were continually made to ensure accessibility through the works. As there were no passing places on the access route, all vehicular movements were required to be meticulously planned. The lack of phone network signal on site meant that portable two-way radio sets and a Starlink internet system were required to facilitate effective communication. 4×4 vehicles were exclusively used to mobilise equipment to the dam crest location.

Permissions and Licenses were obtained to allow the sourcing of water directly from the reservoir to use as drilling flush medium. This avoided the slow transportation of flush medium up the 3km track, maximising drilling productivity.  Excess drilling flush was subsequently transported via 4×4 vehicles to the dam toe and stored in static containers, ready to be collected and disposed of by a licensed waste carrier on completion of the project.

Following the resolution of complex access constraints, Geobor S wireline rotary core drilling techniques were employed at all borehole locations to maintain borehole stability and verticality, while optimising core recovery in the anticipated variable ground conditions. As the concrete clast components and the underlying bedrock was highly abrasive, it was essential for the drilling specialists to select equipment tailored to withstand these challenging conditions, ensuring tool durability and maximising core recovery. In certain areas, ground conditions proved more variable due to the presence of weathered mudstone interbedded with sandstone layers. To better characterise the subsurface conditions, downhole wireline optical imaging and acoustic televiewer surveys were conducted, providing detailed insights into the nature and orientation of fractures within the sandstone strata. Additionally, in situ Schmidt Hammer testing was performed on selected rock outcrops to provide comparative data against laboratory-derived strength parameters.

Upon completion of the borehole construction, 8 vibrating wire piezometers (VWPs) were successfully installed. Prior planning ensured that the borehole diameters were adequate to accommodate dual VWPs within the deeper sandstone strata. The VWP cabling was routed through the dam crest using protective ducting and conduits, securely fixed to the concrete wave wall plinth. Due to limited 4G signal coverage, a remote telemetry system was deemed unfeasible, therefore multi-channel dataloggers were installed within an equipment cabinet located in the draw-off tower and connected to the VWP conduit cabling. The dataloggers were configured to record pore water pressure readings from all eight VWPs at hourly intervals. This setup enables Mott MacDonald Bentley (and Dŵr Cymru Welsh Water following handover) to monitor and assess variations in pore water pressure in response to changing weather conditions and reservoir water levels.

Through effective planning, comprehensive site walkovers, and close collaboration with our technical drilling advisors, GEL successfully acquired high-quality geotechnical samples and data. The subsequent complex stability study conducted by Mott MacDonald Bentley led to a “no build” solution, through providing improved confidence in the dam performance. Not only did this ensure the relevant reservoir safety certificate for the investigation and study was signed off on time, but provided significant cost and carbon savings to Dŵr Cymru Welsh Water.

Elan Valley Aqueduct – Bath Coppice

THE PROJECT

Intrusive ground investigation techniques were required to provide a detailed investigation of the geotechnical & the hydrological characteristics of the underlying material to inform the design and construction of a new large diameter water pipe installation and monitoring of the slope stability during construction.

THE CHALLENGE

Boreholes were located on steep sides of the River Severn Valley with the Severn Valley Railway running directly below the works area. Access to the location for the drill rigs was across numerous sloping fields.

THE SOLUTION

The P60 drilling rig enabled safe access across the fields and then down the valley slopes via radio remote control with the self-levelling support platform creating a safe working area adjacent to the borehole location. The instrumentation was moved to the borehole locations on the slope using the P60 “mule” self-levelling support platform.

Window samples were also required at locations on the slope, our modular rig was transported to each location on the “mule” and set up on level areas along the valley sides.

Installation of the ShapeArray™ monitoring instrumentation was undertaken with support from the supplier. A remote solar power supply and data transmitting point was installed at the top of the slope to send live information on the slope condition.

In total three exploratory boreholes were completed using a P60 slope rig, 2 boreholes using a Comacchio GEO 305 (Pioneer) multipurpose drilling rig. Two window sample holes with the modular window sample rig and two machine excavated trial pits.  A range of drilling techniques including dynamic sampling, and rotary coring with biodegradable polymer flush media were utilised. The boreholes were advanced to the target depths of up to a maximum 40m depth. Geotechnical Laboratory testing (geotechnical and geoenvironmental) was undertaken by GEL and incorporated within a factual report along with the borehole and trial pit logs.

Grafham Reservoir

THE PROJECT

Grafham Water Dam is a 22m high zoned earth fill dam approximately 1.7 km in length. It is located close to the village of Perry, Cambridgeshire adjacent to the Grafham Water Treatment Works. The dam was built between 1962 and 1964, to designs prepared by Binnie & Partners.

During the construction phase, a range of instrumentation was incorporated into the embankment, to permit monitoring of water pressure levels and seepage flows. Following reporting of all data acquired from these geotechnical instruments, it was later recommended that new vibrating wire piezometers (VWP) be installed to replace the existing, ageing hydraulic instruments.

Geotechnical Engineering Limited (GEL) were appointed by Anglian Water Services as Principal Contractor, to deliver the scope of intrusive drilling works on the dam embankment. The data collected from the obtained samples would be utilised to understand the earthworks construction, with the boreholes being installed with specialist equipment for future remote monitoring.

THE CHALLENGE

To achieve an effective monitoring network, a series of boreholes were specified to be constructed across the dam embankment crest, downstream shoulder and embankment toe. The mid-slope positions were located on areas of the embankment with slope angles up to 30°, in locations where traditional geotechnical drilling equipment would be unable to access without significant slope reprofiling.

The proximity of the exploratory positions to a public pedestrian walkway located at the crest of the embankment was a key project Health and Safety risk. The segregation of the public/works interface and continual management would be paramount to the safe delivery of the project.

It was also identified that surface settlement monitoring points that were installed at the time of the construction of the reservoir would need to be considered when moving equipment around site, to avoid disturbance to the apparatus. All site staff were briefed of their location during the site induction process, to ensure their operation remained unaffected during the fieldwork.

THE SOLUTION

It was imperative that a detailed site walkover was undertaken by one of our highly experienced and qualified Drilling Supervisors, to understand the site-specific H & S risks, slope geometry of the downstream shoulder and other access restrictions. This knowledge was utilised by our health and safety and project management teams to develop a site-specific safe system of work.

The positions on the downstream shoulder were completed by one of our awards winning P60 multipurpose slope climbing rigs and ancillary working platform. This approach created a safe working area at the otherwise inaccessible exploratory hole locations, protecting our site staff from risks associated with working on slopes. The rig and support platform were manoeuvred to and between each location using radio remote controls operated by the Lead Driller from an up-slope position of safety.

Detailed soil logging was required of the clay core, embankment fill and Oxford Clay formation, to determine the variability of the dam construction, and to understand the weathering profile beneath the structure of the dam. This was essential to determine the accuracy of the depths of each VWP installation.

VWP’s were installed in the boreholes at varying levels within the embankment structure and within the underlying Oxford Clay formation with the function of measuring the pore water pressures from the core of the dam, below the dam and within the embankment of the downstream face. Down-hole instrumentation was then backfilled using a grout medium to mitigate the creation of any open pathways within the embankment and maintain the embankments structural integrity.

It was identified that a telemetry system that connected the VWP installations to an online, remotely accessible web portal, would have significant benefit to the Reservoirs Safety team.  Several discussions were held between AW and GEL to establish the most suitable system of telemetry equipment, given the lack of network coverage in the area, and to agree the security measures to protect the apparatus.

To limit the impact on the site and keep our works discrete, the monitoring nodes were installed in plastic flush covers. The plastic material was used in this instance to ensure the transmission signals to the Gateway system was not limited. The Gateway was set up immediately to the east of the site in a water treatment works with a maximum distance of around 200m from the furthest node.

With due consideration to the public in mind, the works located on the pedestrian route located at the embankment crest were clearly segregated by physical barriers, with the appropriate signage displayed and diversionary routes clearly visible. This approach limited the impact of our and ensured the safety of both our staff and the public.

Contact us

Centurion House, Olympus Park, Quedgeley, Gloucester GL2 4NF

Jactin House, 24 Hood Street, Ancoats, Manchester, M4 6WX

Send us a message